Pegu Khola Small Hydropower Project

Active

Bigu Hydro Venture logo

Portfolio company

Bigu Hydro Venture

Project overview

A 3.45 MW run-of-river hydropower project advancing headworks, headrace-pipe and powerhouse construction in Bigu Rural Municipality, Dolakha.

Project type
Run-of-River (RoR)
Capacity
3.45 megawatts (MW)
Location
Bigu Rural Municipality, Dolakha District
Development stage
Active
Latest site update
21 August 2026
Headworks
Settling-basin hillside walls for panels 2–4 complete; headpond excavation complete with rebar installation ongoing
Headrace pipe
1,476 m delivered to site; 162 m and three bends erected; 12 bend fittings completed
Powerhouse
Machine-hall bay 02 bottom raft completed; shear-wall reinforcement and formwork ongoing